Proposed road closures
There will be traffic restrictions in place to provide working space and to protect the workforce as follows.
April 24 – May 24
A601(M) / A6070 Lane 1 Closure East and Westbound
(Lane 2 Open with temporary 40mph speed limit.)
June 24 – mid July 24
A601(M) / A6070 Lane 2 Closure East and Westbound
(Lane 1 Open with temporary 40mph speed limit.)
Mid July 24 – February 25
A601(M) / A6070 Lane 1 or Lane 2 Closure East and Westbound as required by the works. (*)
(One lane will remain open with temporary 40mph speed limit.)
Mid July 24 – November 24
Closure of Higher North Road at the Bridge.
(Pedestrian access to be maintained.)
February 25- March 25
Several night time closures during this period.
Exact dates and times of closures and diversion routes for traffic will be publicised well in advance.
(Diversion routes will be signed.)
(*) Some night time closures may be required during this period. Exact dates and times of closures and diversion routes for traffic will be publicised well in advance. (Diversion routes will be signed.)