Construction schedule

There is a lot of preparatory work required before works start on site, however, the current programme of works comprise:

April 24 – May 24

Hard shoulder works
(New verge construction, drainage, safety fencing)

June 24 –  mid July 24

Central Reserve
(Kerbing, drainage, safety fencing)

Mid July 24 – February 25

Higher North Road Bridge
(Concrete repairs and bearing replacement)

October 24 – February 25

Elpha Bridge
(Concrete repairs and parapet replacement)

October 24 – February 25

Brewers Barn East Bridge
(Concrete repairs, bearing replacement and parapet replacement)

October 24 – February 25

Brewers Barn West Bridge
(Concrete repairs, bearing replacement and parapet replacement)

February 25- March 25

Highway Repairs
(Carriageway Resurfacing, road marking and signs)