Approved bridges 2020/21 capital programme

2020/21 maintenance of highway assets

2020/21 Programme: Bridges

Project name Division District Project description Estimate
Mallard Footbridge Morecambe North Lancaster Footbridge Strengthening £22,000
Town End Canal Bridge Morecambe North Lancaster Bridge Strengthening £50,000
Halton Station Bridge Lancaster Rural East Lancaster Bridge Painting £125,400
White Horse Railway Bridge Wyre Rural East Wyre Scheme Development £140,000
Garstang Bridge Wyre Rural East Wyre Scheme Development £18,000
Union Bridge Thornton and Hambleton Wyre Bridge Repairs £47,100
Sykes Cottage Bridge Longridge with Bowland Ribble Valley Bridge Strengthening £192,500
Pinder Hill Bridge Longridge with Bowland Ribble Valley Bridge Strengthening £155,000
Watt Street Bridge Ribble Valley North East Ribble Valley Bridge Strengthening £195,100
Rimington Bridge Ribble Valley North East Ribble Valley Bridge Strengthening £70,800
Peel Road Bridge Fylde West Fylde Scheme Design £20,000
Maudland Road Canal Preston Central West Preston Design £4,200
Hargreaves Railway Footbridge Leyland South/Central South Ribble Scheme Development £9,000
Birch No. 8 Subway Skelmersdale West West Lancashire Design/Bridge repairs £165,100
Moor Street Railway Bridge Ormskirk West Lancashire Design £30,000
Ring O'Bells Canal Bridge West Lancashire East West Lancashire Design £10,000
Wanes Blades Bridge West Lancashire East West Lancashire Bridge Painting £193,800
Hawksclough Footbridge Skelmersdale Central West Lancashire Design £12,000
Carr Brook Close Bridge Clayton with Whittle Chorley Bridge Strengthening £160,100
Alleytroyds Canal Bridge Accrington West and Oswaldtwistle Central Hyndburn Design/Bridge repairs £31,800
Enfield Canal Bridge Great Harwood Rishton and Clayton le Moors Hyndburn Design £15,000
Centenary Way Viaduct Defect search Burnley Central East Burnley Defect Investigation £25,000
Curzon Street Bridge Burnley Central East Burnley Phase 2 of Design £26,000
20/21 The Brig Bridge (St James Street) Burnley Central East Burnley Phase 2 of Bridge Strengthening £276,500
Hapton Station Footbridge Padiham and Burnley Burnley Scheme Development £20,000
Raglan Road Footbridge Burnley Central West Burnley Scheme Development £20,000
Plumbe Street Bridge Burnley Central East Burnley Bridge Painting £144,800
Pendle Water Bridge Pendle Hill Pendle Concrete repairs £80,200
Bridges Structural Maintenance of Highway Structures Countywide as necessary Countywide as necessary Structural maintenance to bridges, footbridges and retaining walls £740,600
Forecast outturn capital expenditure: £3,000,000